The Public Works Department is responsible for the planning, design, permitting and construction of public related infrastructure within the Village. The Department is also responsible for the review and evaluation of infrastructure proposed by private development to ensure uniformity and conformity with Village specifications and standards.
The Department plans for the maintenance, repair and reconstruction of existing facilities as well as the long-range planning for the Village. It is also responsible for the inspection and proper documentation of the Village’s construction projects.
The primary objectives include:
- Provide the most cost-effective method of design and construction of projects.
- Evaluate, analyze and develop projects to maintain, repair or replace the Village’s existing infrastructure in accordance with the 5-yr Capital Improvement Plan.
- Ensure infrastructure is constructed according to Village standards and specifications. And that the completed work is properly documented.
The Department of Public Works, to its best ability, handles much of the design and preparation of plans for the Village’s street and utility improvement projects. For the design of street reconstruction and special projects, the Village will retain a qualified civil engineering consultant to assist with the project as needed. The engineering firms that the Village may contract with as needed include: AECOM, Ayres, Cedar Corporation, JT Engineering, Graef, KL Engineering, McMahon Associates, Mead and Hunt, MSA, RaSmith, Robert E. Lee & Associates, Ruekert Mielke and Strand.
2023 Construction Projects Update (9/18/2023)
2023 Street Reconstruction Projects:
Street Reconstruct Projects are scheduled every other year with the next being 2023.
Due to the age and condition of the pavement and underground public utilities, the Village of Allouez is proposing to reconstruct the following streets in 2023:
-
- Roselawn Boulevard – 1400 feet East of Riverside Drive to Webster Avenue
- Karen Lane- Libal Street to Greenwald Street
- Allouez Terrace – Riverside Drive to Termini
- Jackson Street- Allouez Terrace to Derby Lane
2023 Proposed Street Reconstruction Project Map
Project Scope
In general the street reconstruction work includes:
- Underground work will include the removal and replacement of the watermain
- Sanitary sewer and storm sewer will be televised by the Village to determine existing pipe conditions and the scope of the sewer improvements.
- Installation of new storm laterals and replacement of the existing water and sanitary sewer laterals from the main to the property line.
- Voluntary replacement of private side sanitary sewer laterals.
- Placement of new concrete curb & gutter and driveway aprons to the property line.
- Removal of and placement of new asphalt pavement.
- Evaluation and in some cases construction of new sidewalk.
During the week of August 29th and September 6th the engineering consultant will be completing a topographic survey of the street segments above of which will also include the underground infrastructure. Prior to the survey the underground utilities will be located and marked in the field. To ensure that the reconstruction project properly matches the grade of your property, the topographic survey will extend outward onto your property approximately 10 feet.
Letter to Residents 8/23/22 – Proposed 2023 Reconstruction Project Information
Public Informational Meeting
A public informational meeting will be held on Wednesday, February 22nd, 2023 at the Village Hall, located at 1900 Libal Street. A brief presentation is scheduled to begin at 6 P.M. The remainder of the meeting will follow an informal, open-house format allowing you time to review plans and discuss your questions and concerns with project representatives.
Special Assessments
In accordance with Village Code, the cost to install a new lateral is assessable to the benefited property owner. As a part of the project, any property that currently does not have a storm sewer lateral will be provided one to the property line. The Replacement of existing laterals from the main to the street right-of-way (property line) is not assessed by the Village. There are no other assessable street improvements associated with the project.
Schedule
Weather dependent, construction is anticipated to begin as soon as May and be completed no later than the middle to end of October.
AL-2023-05 Salt Storage Shed Repair Project – Plans and Specifications
- Allouez Village Hall – 1900 Libal St, Green Bay, WI 54301
AL-2023-01 Street Reconstruction Project – Plans and Specifications
- Roselawn Blvd – 1400 ft East of Riverside Dr. to Webster Ave.
AL-2023-02 Street Reconstruction Project – Plans and Specifications
- Karen Ln – Libal St. to Greenwald St.
- Allouez Ter – Riverside Dr. to Termini
- Jackson St – Allouez Ter. to Derby Ln.
2023 Street Resurfacing Project
On an annual basis, as part of our road maintenance program, the Village resurfaces a number of streets. The maintenance is necessary to preserve and prolong the life of existing asphalt pavements. With favorable contractor pricing, the Village is proposing to resurface the following streets in 2023: In the event the bid pricing is less than estimated, alternate street projects are being bid.
- Longview Ave. – Libal St. to E. River Dr.
- Mission St. – Webster Ave. to Libal St.
- Derby Ln. – Riverside Dr. to Webster Ave.
- Bid Alternate No. 1 – Kenney St. – Libal St. to Jenkel Ter.
- Bid Alternate No. 2 – Van Buren St. – Allouez Ter to Derby Ln
In general, the street resurfacing project includes:
- Removing and milling asphaltic surfaces.
- Shaping and compacting existing aggregate base.
- Spot repair of storm inlets.
- Spot repair of concrete curb and gutter.
- Reconstruction of manholes.
- Adjustment and placement on inlet and manhole covers.
- Asphaltic pavement.
Weather permitting, work is anticipated to begin in May or June of 2023. Once work begins on a street, the contractor has 30 days to complete all work on that street.
The maintenance work is not special assessed to abutting property owners.
AL-2023-03 Street Resurfacing Project
AL-2023-03 Complete Bid Tab Summary
The plans and specs for the 2023 Sanitary Sewer Lining Project – AL-2023-04 can be found here.
- Roselawn Blvd – +/- 1400 feet east of Riverside Drive to Webster Ave
2022 Construction Projects
-
- AL-2022-01 Street Resurfacing Project
- Project ID 4579-01-71: Doty- Safe Route to School (SRTS) Sidewalk Project
- AL-2022-02 14-inch Watermain Repair Project
Construction Update (9/12/2022)
2022 Construction Projects Map
Upcoming Street Resurfacing Projects (AL-2022-01):
- Jenkel Terrace & Gwynn Street- Lebrun St to Libal St
- Patrick Court- Hoffman Rd to Termini
- Michael Court- Hoffman Rd to Termini
- Dauphin Street- Webster Rd to Libal St
- Rustic Oaks Court- Kalb Ave to Termini
- Hastings Street- Webster Ave to S Irwin Ave
- Letter to Residents – March 25, 2022
Alternate Streets
- Kenney Street- S Clay St to Delahaut St
- Kenney Street- Libal St to Jenkel Ter
In general the street resurfacing project includes:
- Removing and milling asphaltic surfaces.
- Shaping and compacting existing aggregate base.
- Spot repair of storm inlets.
- Spot repair of concrete curb & gutter.
- Reconstruction of manholes.
- Adjustment and placement on inlet and manhole covers.
- Asphaltic pavement.
Weather permitting, work is anticipated to begin in May or June of 2022. Once work begins on a street, the contractor has 30 days to complete all work on that street.
The work will not be special assessed to the property owners as it is part of our annual road maintenance program.
The Plans and Specs for the AL-2022-01 Street Resurfacing Project can be found here.
AL-2022-01 — Complete Bid Tab Summary
Project ID 4579-01-71: Doty- Safe Route to School (SRTS) Sidewalk Project
All work shall be completed by September 16th, 2022.
- Installation of sidewalk along the west side of East River Drive from Lebrun St to Hoffman Rd.
- Installation of sidewalk along the north side of Longview Avenue from E River Dr to Doty Elementary School.
In general the Doty- Safe Route to School (SRTS) Sidewalk Project work includes:
- Installation of a 5’ wide concrete walkway generally located 6’ from the existing back of curb.
- Installation of ADA compliant curb ramps.
- Spot repair to existing inlets and manholes.
- Reconstruction of existing driveway aprons affected by the sidewalk.
- Landscaping and restoration to affected areas.
This is a federally funded project.
The Plans and Specs for the Doty- SRTS Project can be found here.
Doty SRTS — Complete Bid Tab Summary
AL-2022-02 14-Inch Watermain Repair Project
In general the watermain repair work under this contract consists of the following:
- Horizontal directional drilling of 600 feet of 14-inch HDPE watermain
- Installation of valves
- And all preparatory work to reinstate repaired watermain
Work on this project is anticipated to begin this spring, however commencement of this project will depend upon material availability. Once the work begins, all work must be completed in 15 working days. Village desires to have all work completed by June 24th, 2022.
This project is located west of Webster Ave., south of Woodview Ln, east of Beaumont St, and north of Hwy 172 on WDOT right-of-way.
The Plans and Specs for the 14-Inch Watermain Repair Project can be found here.
Street Reconstruction Projects:
Street Reconstruct Projects are scheduled every other year with the next being 2023.
Due to the age and condition of the pavement and underground public utilities, the Village of Allouez reconstructed the following streets in 2021:
- Roselawn Boulevard from Riverside Dr. east approximately 1400 feet.
- Beaumont Street from Greene Ave. north to Mission St.
- Kalb Avenue from Libal St. to the East River
Project Scope
In general the street reconstruction work included:
- Replacement of the existing water main, sanitary sewer and storm sewer.
- Installation of new storm laterals and replacement of the existing water and sanitary sewer laterals from the main to the property line.
- Voluntary replacement of private side sanitary sewer laterals.
- Placement of new concrete curb & gutter and driveway aprons to the property line.
- Removal of and placement of new asphalt pavement.
- Evaluation and in some cases construction of new sidewalk.
2021 Construction Projects Update
Map of 2021 Public Works Projects
2021 Street Reconstruction Plans:
2021 Street Reconstruction Project – AL-2021-01
- Beaumont St- Greene Ave to E. Mission Rd +/- 2,100 ft
- Kalb Ave- Libal St to Termini +/- 950 ft
2021 Street Reconstruction Project – AL-2021-02
- Roselawn Blvd- Riverside Dr east +/- 1,400 ft
2021 Street Resurfacing Project – AL-2021-03
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Rosemont Dr- Webster Ave to Arbor Lane +/- 1,425 ft
- Kalb Ave- Webster Ave to Libal St +/- 2,500 ft
Alternates:
- Hilltop Dr– Clay St to Delahaut St +/- 960 ft
- McCormick St– Clay St to S. Irwin Ave +/- 1,620 ft
- St. Joseph St Alley- +/- 150 ft
2021 Sanitary Sewer Lining Project – AL-2021-04
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Roselawn Blvd – Riverside Dr east +/- 1,400 ft
- Sioux Ln – In easement between Sioux Ln and Beaumont St
2021 Sanitary Lateral Replacement Project – AL-2021-05
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Green Isle Park
2021 Webster Avenue Sanitary and Storm Sewer Televising Project – AL-2021-07
- 25,000 Linear Feet of Sanitary and Storm Sewer
- 225 Sanitary Sewer Laterals
2020 Sanitary Sewer Lateral Replacement Project
-
- St. Mary’s Blvd – Riverside Drive to 1600′ East
2020 Sanitary Sewer Lining Project
- St Mary’s Blvd– Riverside Drive to 1600′ East
2020 Street Resurfacing Project:
- St. Mary’s Blvd – Riverside Drive to 1600′ East
- Stanton Court- Arbor Lane to Termini
- Arbor Lane- Stanton Court to Rosemont Drive
- Garland Street- Webster Avenue to Baird Street
AL-2020-01 Bid Tabulations
2019 Street Construction Project Update
AL-2019-01, 2019 Street & Utility Reconstruction Project:
-
- Oakwood Avenue – Greene Avenue to Allouez Avenue
- Oak Hill Drive – Beaumont Street to Oakwood Avenue
- Summit Street – Beaumont Street to Oakwood Avenue
- Blackhawk Drive
AL-2019-02
-
- Longview Avenue – Delahaut Street to Libal Street
- Martha Avenue – Dead End South 60 Feet
- St. Joseph Street – Riverside Drive to Webster Avenue
2019 Street Repair (Maintenance) Project included the following streets:
AL-2019-03
- Warren Court – Riverside Drive to Du Charme Lane
- Woodrow Way and Brookridge Street – Dauphin Street – Libal Street
- Beaupre Street – Webster Avenue to Libal Street
2019 Street Construction Project Update
2018 Water Main Replacement:
Warren Court Water Main Replacement AL-2018-02
Warren Court from Du Charme Lane to Riverside Drive
2018 Street Repair Projects included the following streets:
East River Drive from Longview Avenue to Village Limits
Floral Drive/Schroeder Lane from Libal Street to St. Joseph Street
Warren Court from Du Charme Lane to Riverside Drive
Service Road from Riverside Drive to Stambaugh Road
AL – 2018 – 01 Bid Tabulations
AL – 2018 – 01 Letter to Resident
2017 Street Repair Projects included the following streets:
East River Drive from E. Briar Lane to Longview Avenue
E. Briar Ln. from Briar Terrace to E. Briar Lane- 700 Block Full Length of street but ½ width:
Le Brun Street from Webster Avenue to McCastlen Street – Joint project with the City of De Pere
AL 2017 – 01 Bid Tabulation
AL 2017 – 01 Bid Tabulation
2017 Street and Utility Reconstruction Project included the following streets:
E. St. Joseph Street from Libal Street to East River Drive
Jourdain Lane from Dauphin Street to Brookridge Street
DuCharme Lane from Iroquois Avenue to Whitney Street
Bryan Street from Linck Court to Webster Avenue
Detrie Drive from S. Clay Street to Delahaut Street
Longview Avenue from S. Clay Street to Delahaut Street
Green Isle Park Entrance
2017 Memo on Sidewalks on Longview and E St. Joseph
Five-Year Reconstruction Plan Meeting July 2016
July 2016 Reconstruction Meeting Memo
July 2016 Reconstruction Plan Meeting Input Form
July 2016 Reconstruction Plan Power Point Presentation
2016 Map of Street Repair Projects
2016 Letter to Resident Effected by Street Repair Project
2016 Street Repair Projects included the following streets:
Miramar Drive from Du Charme Lane to Riverside Drive
Hawthorne Place from Allouez Avenue to Meadow Lane
Chantilly Rue from Bordeaux Rue to Grande Rue
East River Drive from Hoffman Road to East Briar Lane
**East Briar Lane from Libal Street to the 700 Block of Briar Lane: Length of street but ½ width: Alternate (If funds are available after bid opening)
AL 2014 – 1 A and B Bid Tabulations
AL 2014 – 02 Bid Tabulations
If you have not filled out a Bidder’s Proof of Responsibility for the Construction Year, please click on the link – Bidder’s Proof of Responsibility